Add 'Sub Job' Segment Items to a Procore Project

Objective

To add a sub job to a Procore project in the Work Breakdown Structure (WBS) page of the project's Admin tool. 

Background

After a sub job has been created, you can issue specific line items on the Schedule of Values (SOV) for a change order to the sub job.

Things to Consider

Prerequisites

Steps

  1. Navigate to the project's Admin tool.
  2. Under 'Project Settings', click the Work Breakdown Structure link. 
  3. In the 'Segments' table, click the Sub Jobs link.
     Notes
  4. Choose from these options:
    • If you are creating sub jobs for the first time, click the Add Segment Items button. 
      OR
    • If you are adding sub jobs to an existing list, click the Add Item button. 
  5. Enter the following information:
    • Code. Enter an alphanumeric code for the sub job. 
    • Description. Enter a description for the new sub job. 
  6. Click anywhere outside the line item to save it.
    Procore displays the work 'Saved' in GREEN text.  
     Important

    As shown below, after you add the 'Sub Job' segment to a project, it will automatically be added to the 'Segments' table in the Company level Admin tool with a tooltip beside it. Adding the 'Sub Job' to a project counts as using one (1) of your company's thirteen (13) available segments. 

    wbs-sub-jobs-in-segment-table.png