Add a Line Item to a Commitment's Schedule of Values
                
                Background
After you create a commitment, use the steps below to add line items to the Schedule of Values. 
Things to Consider
    - Required User Permissions:
    
        - 'Admin' level permissions on the project's Commitments tool.
 
- Additional Information:
    
    
- 
    
    
Steps
    - Navigate to the project's Commitments tool.
- Under the Contracts tab, locate the commitment to update. Then click Edit.
- Click Schedule of Values.
- Click Add Line.
    
    
- Follow the appropriate steps depending on whether your accounting method is Amount Based or Unit/Quantity Based:
    
    
        - For contracts using the Amount Based accounting method:
        
            - #
 Automatically enters a line item number in sequential order.
- Change Event Line Item
 If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
- Budget Code
 Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?
- Description
 Enter a description for the line item. For example, type: Monthly Service Fee
- Amount
 Enter the amount of the cost.
- Billed to Date
 The system automatically calculates the amount billed on the commitment up to the current date.
- Amount Remaining
 Enter the amount that has NOT been billed to the current date.
- Tax Code
 Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
 
- For contracts using the Unit/Quantity Based accounting method:
        
            - #
 Automatically enters a line item number in sequential order.
- Change Event Line Item
 If you have change events enabled, you can select a change event line item if the commitment needs to be linked to a change event.
- Budget Code
 Select a budget code from the list or click Create Budget Code to create a new one. See What is a budget code in Procore's WBS?
- Description
 Enter a description for the line item. For example, type: Monthly Service Fee
- Qty
 Enter the number of units.
- UOM
 Enter the Unit of Measure (UOM).
- Unit Cost
 Enter the Unit Cost in the box provided.
- Amount
 The system automatically calculates the subtotal for you, based on the Qty, UOM, and Unit Cost entries.
- Billed to Date
 The system automatically calculates the amount billed on the commitment up to the current date.
- Amount Remaining
 Enter the amount that has NOT been billed to the current date.
- Tax Code
 Enter a tax code to use for this line item. This field only appears if you have enabled the tax codes feature. See How can I use tax codes on a project?
 
 
- Choose one of these options:
    
        - Save. Click this button to save the changes to the SOV. 
- Save & Email. Click this button to save the change to the SOV and email the updates to the invoice contact.