This workflow allows customers, without Procore Project Financials, to upload budgeted labor hours and production quantities without using the Budget tool.
After your hours are budgeted and production quantities are established, your field teams can use Timesheets to record time against these budgeted tasks and submit and add quantities for the units installed daily in Timesheets.
In reporting, your imported budget can be used in the Labor Budget to Actual Report, where users can compare timecard hours entered in Procore with the labor hours in your imported budget. The primary value of this report is to see the percentage of hours used for each cost code, and includes calculated values like remaining hours, and job to date hours.
For production quantities, your imported budget can be used in the Field Production Report, where users can compare production quantities entered in the Timesheets tool with the production quantities in your imported budget. The primary value of this report is to track the progress of products installed on site by seeing the percentage completed for each cost code. It also includes calculated values like budgeted, actual, and remaining quantities. This gives the teams real-time insight into the percentage of work completed for tasks on site.
To take the steps in this guide, users need the following permissions:
Company Level
Project Level
Some of these tasks can be performed with lower level or granular permissions. See the User Permissions Matrix for the full list of actions taken in all other tools.
For customers with Resource Tracking and Project Financials, you can track and manage your production quantities in your budget.
You can leverage flexible Work Breakdown Structure (WBS) when budgeting the resource hours and associated cost, as well as a production plan based on units to install for production quantities. Flexible WBS allows your team to budget, track time and units installed in Timesheets, and report at the right level of granularity, for an enhanced real time labor productivity cost Budget View.
You can also set up a budget view named 'Procore Labor Productivity Cost' budget view. This is a pre-built view that you can quickly add to a project. It allows users to input production quantities to your project's budget.
This guide walks you through how to:
Assign the Default Cost Type for timecard entries in the Company Timesheets tool.
To configure additional settings, see Configure Advanced Settings: Company Level Timesheets.