Enable Sub Jobs on Projects for WBS

Objective

To enable the company level setting that allows your team to use the project level Sub Jobs feature with Work Breakdown Structure (WBS).

Background

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the Company level Admin tool.
  • Additional Information:
  • Limitations:
    • For customers using the Company level ERP Integrations tool
      The default segments in WBS are compatible with Procore's ERP Integrations tool. However, some integrations do NOT yet support custom segments. To learn more, see Things to Know about your ERP Integration.
    • For customers who have independently developed or purchased a third-party solution to integrate with Procore
      To take advantage of the custom segment capabilities associated with WBS, any existing API integrations that you have independently developed or purchased to interact with Procore must be updated to support Procore's new WBS API.

Steps

  1. Navigate to the Company level Admin tool. 
  2. Under 'Company Settings', click Work Breakdown Structure.
  3. Click the Configure Settings icons-settings-gear.png icon. 
  4. Check the box under Sub Jobs. 
  5. Click Save.