Create a Prime Contract Change Order

Objective

To create a prime contract change order in the Project level Prime Contracts tool. 

Background

Use the steps below when you need to create a prime contract change order.

Things to Consider

  • Required User Permissions:
    • 'Admin' level permissions on the project's Prime Contracts tool.
  • Additional Information:
  • For companies using the icon-erp-synced2.png ERP Integrations tool: Show/Hide  
    • Not all ERP integrations support the sync of change orders. For those that do, additional requirements, limitations, and considerations vary depending on the ERP system your company's account is integrated with. See Things to Know About your ERP Integration for details.

Prerequisites

Steps

  1. Navigate to the project's Prime Contracts tool.
  2. Locate the prime contract to work with. Then click its Number link. 
  3. Click Create Prime Contract CO.
    create-prime-contract-change-order.png
  4. Complete the following fields:
    •  
    • Depending on the change order tier settings of the Prime Contract's tool, one (1) of these list boxes will appear:
      • OR
  5. Choose one (1) of these options:
    • To create the change order, click Create.
      OR
    • To create the change order and send email notifications, click Create & Email. 
      OR
    • If you are using the Procore + DocuSign® integration to collect signatures, click Complete with DocuSign. To learn more, see DocuSign®.