How can I set up a tenant construction chargeback in the Cost Tracker?
Answer
Follow the steps below:
- Navigate to the Cost Tracker for the project.
 - Click Add Cost Item and enter 'Tenant Chargeback' as the name. See Add a Cost Item to the Cost Tracker.
 - Click the arrow 
 icon next to the cost item and select Add Contract.

 - On the contract's setup page:
    
- Enter $0 as the Total Contract Value.
 - Click the toggle under Cost Breakdown to the OFF position.
 - Select the tenant's name in the Vendor field.

 
 - Click Continue and exit out of the Share Contract modal (so that you do not share the contract with the tenant).
 - To reflect a cost charged back to the tenant, add a negative change order and mark that change order as approved. Be sure to give a reason to approve the change order.

 - Upon approval, the Cost Tracker will reflect a reduction in the overall committed amount, which is a cost that would be incurred by the tenant.
 