Project Schedule
- Last updated
- Save as PDF
The Schedule tool enables you to keep your team up-to-date by giving them a real-time view of the current project schedule. You can create, edit, and share schedules, along with integrating your Primavera P6 or MS Project schedules.
- Import existing schedules created in Microsoft Project, Primavera P6, and the MPX file format
- Create and assign public or private calendar items to Procore users and project contacts
- Evaluate all of a project's scheduled tasks or narrow the field in view by day, week, month or as a Gantt chart
- Track, view, and monitor progress by resource group or for individuals
Popular Tutorials (view all)
Top FAQ (view all)
- Which Procore tools support granular permissions?
- Which emails are affected by the updated inbound email communication settings in Procore?
- Does the master schedule update when I make a change to a Lookahead schedule?
- How do I edit a project schedule in Procore?
- What is a construction project's schedule?
Brak pozycji odpowiadających Twojemu zapytaniu.
Note
See Procore Imports for additional videos related to the Schedule tool.Wskazówka
Aby przeglądać i przeszukiwać wszystkie filmy szkoleniowe Procore, odwiedź naszą bibliotekę filmów.
- Can I export a Lookahead schedule?
- Can I update the Percent Complete field on the Procore web application?
- Does the master schedule update when I make a change to a Lookahead schedule?
- How can I troubleshoot an issue with the Procore Web Application?
- How do I edit a project schedule in Procore?
- How do I get the percent complete updated in the native schedule file?
- Should I integrate my Microsoft Project Schedule in Procore's web application or Procore Drive?
- What granular permissions are available for the Project level Schedule tool?
- What is a construction project's schedule?
- Which Microsoft Excel file versions can be attached to items in Procore?
- Which Procore tools support granular permissions?
- Which emails are affected by the updated inbound email communication settings in Procore?
- Which versions of Microsoft Project does Procore support?
- Why is the delete button dimmed and not available in the Schedule tool of Procore Drive?
Schedule
Important
Permissions
What granular permissions are available for the Project level Schedule tool?
| Action | None | Read Only | Standard | Admin | Notes |
|---|---|---|---|---|---|
|
Add Related Items to a Scheduled Task |
|||||
|
Configure Advanced Settings: Schedule |
|||||
|
Configure Schedule Notification Emails |
|||||
|
Configure the Project Level Schedule Tool for Primavera P6 |
|||||
|
Clear an Integrated Schedule |
|||||
|
Create a Calendar Item |
|||||
|
Create Lookahead |
|
|
|||
|
Create Lookahead Tasks |
|
|
|||
|
Delete Calendar Item |
|||||
|
Delete Lookahead |
|
|
|||
|
Delete Lookahead Tasks |
|
|
|||
|
Edit Any Calendar Item |
|||||
|
Edit a Calendar Item You Created |
|||||
|
Edit Lookahead Task |
|
|
On a mobile device, this action can be performed offline if the item was previously viewed and cached on your mobile device. Tasks performed offline sync with Procore when a network connection is reestablished. | ||
|
Export a Project Schedule |
|||||
|
Request a Schedule Change |
|||||
|
Search and Filter for Scheduled Tasks |
|||||
|
Send Recurring Project and Resource Schedules |
|||||
|
Update a Project Schedule File |
|||||
|
Update Lookahead Tasks |
|
|
|||
|
Update Task Completion Percentage |
|
|
|||
|
Upload a Project Schedule File to Procore's Web Application |
|||||
|
Upload an Asta Powerproject Schedule |
|||||
|
View a Project Schedule |
|||||
|
View a Scheduled Task |
|||||
|
View Lookahead |
|||||
|
View the Change History of Lookaheads |
|
|
Below are the notable changes to the Project level Schedule tool.
Recent Changes
New lookahead schedule Options (01/08/2024)
Procore has updated the project level Schedule tool to now give you the option to create a follow-up lookahead that only pulls tasks from your schedule while ignoring the previous lookahead information. Previously, Procore pulled in tasks and changes from the previous lookahead as well. See Create a Lookahead Schedule.
Project Level schedule settings modernization (12/21/2023)
Procore has made several design changes to the project level Schedule tool settings. Changes include a modernized navigation menu, new tabs that provide a more simplified and consistent experience, and updated user permission settings. See Schedule: Project Level Schedule Settings Modernization for more detail.
Modernized Calendar View (05/17/2023)
Procore has updated the the Project level Schedule tool with a modernized calendar view, filters, and create and edit experience. Learn more in the Announcement and see, Create a Calendar Item, and Search for and Filter Calendar Tasks.